Incentive Hub POC
GearVN — Hệ thống quản lý thưởng
🏠 Tổng Quan
📅 Timeline
✅ Tasks
📄 Tài Liệu
⚡ Quyết Định
⚠️ Rủi Ro
👥 Team
🟡 Phase 6D
Phase 6 — Build PRD v2.3
Incentive Hub POC
Target: 07/04/2026 — POC Complete
45%
Phase 6 Progress
20
Tasks Done
17
Tasks Remaining
4
Pending Items
OVERALL PROGRESS — PHASE 6
45%
6A ✅ DB · 6B ✅ Backend · 6C ✅ API
6D ⚪ Frontend · 6E ⚪ Data · 6F ⚪ QA
✅
Task Board
37 tasks · 20 done
📅
Timeline
6 phases · Phase 6 active
⚡
Quyết Định
Key decisions log
⚠️
Rủi Ro
4 pending items
👥
Team
5 members
📄
Tài Liệu
PRD, specs, analysis
📋 Phase 6 — Sub-phases
Phase
Nội dung
Status
6A
Database + Ceiling Engine
✅ DONE
6B
Backend Logic (6 modules)
✅ DONE
6C
API Routes (14 endpoints)
✅ DONE
6D
Frontend Pages (9 pages)
⚪ TODO
6E
Data Migration
⚪ TODO
6F
QA + Deploy
⚪ TODO
❓ Pending — Chờ Stakeholder
Q3: 23% NV giảm >25%
Chờ CEO + HR · Ảnh hưởng budget
Q7: GP refresh rule
Chờ PM Head
Q8: ONL vs OFF per-unit
Chờ CEO + HR
379 SKU thiếu Bộ giá
Chờ Chị Quý
📝 Hoạt Động Gần Đây
26/03
📊
Ní
— Check Tier Base per SKU cho 1,298 mã (yêu cầu từ chị Quý)
26/03
💰
Ní
— Query thưởng ưu đãi bán hàng T1-T12/2025 từ StarRocks
24/03
✅
Phase 6A-6C
— Hoàn thành DB + Backend + API (14 endpoints)
24/03
🗄️
Anh Tài
— Schema v2.3 finalized (15 tables, 351 lines)
17/03
📋
Sprint
— Re-plan Phase 6 timeline, target 07/04
15/03
📄
PRD v2.3
— Finalized fund ceiling design (§3.3)
07/03
🚀
Project
— Kickoff Incentive Hub POC · Ní joined team
Cập nhật tự động bởi Ní (Incentive Hub Assistant) —
🏠