Phase 6 — Build PRD v2.3

📅 Sprint Timeline

07/03 → 07/04/2026 · 6 Phases · Target: POC Complete

✅ Phase 0-5 — Completed
✅ DONE
Phase 0-3
07/03 – 14/03
DATA · CORE ENGINE · UI DEMO · E2E TEST
📋 Setup + Calculator + 5 pages + 14 DC
✅ DONE
Phase 4
14/03 – 15/03
ANALYSIS & PRD
📄 PRD v2.3 + Analysis v5.0 + 13 docs
✅ DONE
Phase 5
15/03 – 17/03
FUND CEILING DESIGN
💰 PRD §3.3 Ceiling spec + Re-plan
🔥 Phase 6 — Build PRD v2.3 (Active)
✅ DONE
6A-C
17/03 – 24/03
DB + BACKEND + API
🗄️ Schema 15 tables · 6 modules · 14 APIs
⚪ NEXT
6D
30/03 – 03/04
FRONTEND PAGES
0/9 pagesAnh Tài
⚪ PENDING
6E-F
04/04 – 07/04
DATA MIGRATION + QA + DEPLOY
📦 Seed D1 · Smoke test · QA · Deploy CF
🏁 Milestones
M1: Core Engine Complete
24/03 — Schema + Backend + API done
M2: UI Complete
03/04 — 9 frontend pages
M3: POC Go-Live
07/04 — Deploy + QA pass
Cập nhật bởi Ní —